Major Renewal of Nishinomiya Chuo Sports Park Delayed by Three Years

This page is automatically translated. Please refer to the original Japanese for accuracy.
はまぁむ@にしつーサポーター
にしつー

Nishinomiya Central Sports Park’s major renovation appears to be delayed by about three years.
(Information provided by Sasako @ Nishitsu SP)

The image below is quoted from About the Nishinomiya Central Sports Park Redevelopment Project | Nishinomiya City Website.

Here it is↓

During a survey to check for buried cultural properties conducted at the planned construction site in fall 2024, it seems that manyartifacts dating from the Kofun period through the early modern period were discovered🏺🙌

Because of this, a further full-scale excavation survey will be carried out.

The completion of the entire park is expected to be delayed by three years, with completion now projected for around March 2032.

Here it is on the map↓

The address is 2-7 Kawahara-cho, Nishinomiya City, Hyogo Prefecture.

So what did they find?

Here is the artifact found during the excavation survey↓

It looks like a jar called Sue ware (sueki). The kind we learned about in school way back when〜😆

Here’s what the excavation site looks like↓
The moment history emerges from the soil… there’s something so romantic about it〜😍

They are also considering holding an exhibition of the artifacts found during the excavation at the local history museum, as well as an on-site briefing session.

What’s the schedule going forward?


*Latest redevelopment project schedule as of May 2025

According to the current schedule,

  • Around July 2025: Preparatory work begins to drain spring water
  • Around September 2025: Full-scale excavation survey (Phase 1) begins〜
  • Until around 2027: Careful excavation over roughly two years
  • From 2027 onward: The existing gymnasium will be demolished, followed by Phase 2 excavation
  • Around March 2032: Completion of the entire park (about three years later than originally planned)

During the excavation survey, it seems that other redevelopment work will continue in parallel wherever possible〜🙌

By the way, here’s what the completed layout is expected to look like↓

For the detailed plan, see below↓
About the Nishinomiya Central Sports Park Redevelopment Project | Nishinomiya City Website

Nishitsu has also put together a summary here↓

Nishinomiya Central Sports Park to Undergo Major Renewal with Completion Planned Around 2029

2023年5月2日

Finally

The park was originally scheduled to be completed in October 2025, but the final timeline now points to 2032. In the end, that means a delay of about seven years. Incidentally, 2032 is also when the redevelopment around Hanshin Nishinomiya is scheduled to be completed〜! It feels like there may be new discoveries in Nishinomiya, kind of like the site of the new hospital near Hanshin-Kokudo😊 It would be exciting if this turned into a major discovery for the ages. We’ll share more updates on Nishitsu as soon as we hear anything〜

*Sasako @ Nishitsu SP, thank you very much for the tip!!
■■■We’re looking for tips!■■■

西宮市の求人情報

「日勤のみ」正看護師・准看護師/保育園・学校/常勤・日勤のみ
リッツ荒木杜保育園 兵庫県 西宮市
月給25万円~
「駅チカ」看護師/企業主導型保育事業
株式会社アーク 兵庫県 西宮市
月給25万円~
保育士/認可保育園の見守り保育/兵庫県西宮市
株式会社ウィルオブ・ワーク キッズケア営業部 兵庫県 西宮市
時給1,700円~
年齢不問の保育士 ブランク20年以上も活躍中
株式会社ニッソーネット 兵庫県 西宮市
時給1,650円~
「有資格」調理師/保育園/門戸厄神駅
ポストメイト保育園・門戸厄神 兵庫県 西宮市
月給22万6,000円~
Sponsored by 求人ボックス