Road Closures Planned Around Koshien Stadium Starting Around October

This page is automatically translated. Please refer to the original Japanese for accuracy.
しゃちょ美@にしつー
にしつー

It looks like there will be road closures around the outside of Hanshin Koshien Stadium.
(Information provided by Chibimarue-san)

The notice↓

The closures appear to be related to expansion work on the “Ginsan” roof over the stadium’s infield seats.

Hanshin Koshien Stadium’s Alps Stand Looks Set to Be About 70% Covered

2024年8月17日

Overall Schedule for the Ginsan Roof Expansion Work

The work will be carried out in four phases and proceed during the professional baseball off-season


Quoted from the PDF: Hanshin Koshien Stadium Will Extend the Ginsan Roof to the Alps Stand — Carrying on its history as the sacred ground of baseball while preserving high school baseball culture

This time, STEP 1, the foundation work, will be carried out. Completion is scheduled for 2028. Since the work is only done during the off-season, it will take quite a while.

Current Road Closure Schedule

Mizuno Square Side

Scheduled road closure dates

November 3, 2025 – March 5, 2026 (right-field side / first-base side)

South Side / Upper Right Side

Scheduled road closure dates

October 3 – 14, 2025 (around the left-field side / third-base side)

October 21 – 27, 2025 (also on the third-base side)

November 3, 2025 – March 5, 2026 (left-field side / first-base side)

*The road closure periods may be subject to change.

Lastly

The period from November 2025 to March of the following year is fairly long, so if you usually pass through the stadium area to get to Corowa or the station, please take note.

*Thank you, Chibimarue-san, for the information!!
■■■We’re looking for your tips!■■■

西宮市の求人情報

介護職員/介護福祉士/交通費支給/再雇用制度有/年休110日以上/サービス付高齢者住宅
サービス付き高齢者向け住宅 清和の郷 兵庫県 西宮市
月給24万7,300円
調理見習い
すき焼き・しゃぶしゃぶ すみれ 阪急西宮ガーデンズ店 兵庫県 西宮市
月給25万円~
アイリスト/西宮北口駅/兵庫県/西宮市
EyeFlash阪急西宮ガーデンズ店 兵庫県 西宮市
月給20万円~45万円
Sponsored by 求人ボックス