It looks like the Harukaze Elementary School building will be rebuilt as a new 4-story structure. The new school building is expected to be completed in January 2021.
The plans are below ↓
Nishinomiya Municipal Harukaze Elementary School Educational Environment Improvement Project Basic Design and Implementation Design Materials – Nishinomiya City Board of Education, School Facilities Planning Division
目次
The new school building will have an atrium, courtyard, and rooftop pool
The new school building will be 4 stories tall and will apparently be built on the north side of the school, facing “Kawarabayashi Park.”
The new school building will be completed in January 2021, but the demolition of the old building and full improvements to the playground and other areas are scheduled to be fully completed in July 2022.
The new school building will have features like a courtyard, a rooftop pool, and greenery, so it seems like a building worth looking forward to. The project cost appears to be 2.48 billion yen.
Brand-new facilities in the new school building
- Courtyard
- Rooftop pool
- Lunch room / exchange hall
- Playroom
- Open space
- Terrace
- Atrium
Brand-new facilities outside the building
- Foot-washing and hand-washing area
- Tire play area
- Swings x 2
- Half-height climbing pole
- Monkey bars
- Sandbox
- High and low horizontal bars
- Jungle gym
- Basketball stand
- 4 soccer goals
Other newly built structures
- Childcare center building
- Clubhouse building / community exchange building
Existing facilities that will remain
- Gymnasium
- Emergency water storage tank
Construction to begin around summer vacation
Construction is scheduled to begin around summer vacation, and during the construction period, the playground will be about half its current size.
The old school building will be demolished
The old school building on the south side will apparently be demolished. It must feel a little sad for those who were attached to it.