Harukaze Elementary School Building to Be Rebuilt as a New 4-Story Facility Slated for Completion in Late January 2021

This page is automatically translated. Please refer to the original Japanese for accuracy.
しゃちょう@にしつー
にしつー

It looks like the Harukaze Elementary School building will be rebuilt as a new 4-story structure. The new school building is expected to be completed in January 2021.

The plans are below ↓

Nishinomiya Municipal Harukaze Elementary School Educational Environment Improvement Project Basic Design and Implementation Design Materials – Nishinomiya City Board of Education, School Facilities Planning Division

The new school building will have an atrium, courtyard, and rooftop pool

The new school building will be 4 stories tall and will apparently be built on the north side of the school, facing “Kawarabayashi Park.”

The new school building will be completed in January 2021, but the demolition of the old building and full improvements to the playground and other areas are scheduled to be fully completed in July 2022.

The new school building will have features like a courtyard, a rooftop pool, and greenery, so it seems like a building worth looking forward to. The project cost appears to be 2.48 billion yen.

Brand-new facilities in the new school building

  • Courtyard
  • Rooftop pool
  • Lunch room / exchange hall
  • Playroom
  • Open space
  • Terrace
  • Atrium

Brand-new facilities outside the building

  • Foot-washing and hand-washing area
  • Tire play area
  • Swings x 2
  • Half-height climbing pole
  • Monkey bars
  • Sandbox
  • High and low horizontal bars
  • Jungle gym
  • Basketball stand
  • 4 soccer goals

Other newly built structures

  • Childcare center building
  • Clubhouse building / community exchange building

Existing facilities that will remain

  • Gymnasium
  • Emergency water storage tank

Construction to begin around summer vacation

Construction is scheduled to begin around summer vacation, and during the construction period, the playground will be about half its current size.

The old school building will be demolished

The old school building on the south side will apparently be demolished. It must feel a little sad for those who were attached to it.

 

 

 

 

 

西宮市の求人情報

病院の看護師/准看護師
医療法人社団清和会 笹生病院 兵庫県 西宮市
時給2,105円
栄養士/急募/日勤パート/夜勤なし/駅チカ/研修支援有
サンケア上甲子園 兵庫県 西宮市
時給1,218円~1,458円
スポットで働く美容師/週1日×1日3時間から働ける!/ブランクからの復帰や家事・育児との両立可
カットカラー専門店チョキぺタ 西宮今津店 兵庫県 西宮市
時給1,240円~1,380円
病院/正看護師/夜勤アルバイト
渡邊高記念会 兵庫県 西宮市
日給3万5,000円
「保育園・幼稚園」有資格/栄養士/今津駅 徒歩12分
用海山水保育園 兵庫県 西宮市
時給1,150円~
Sponsored by 求人ボックス